Tasman Bridge

Aqua Prep was engaged to remove the existing render that was protecting the the bridge on nine columns that were to have a new cathodic protection system installed, working from a boom lift (EWP) Aqua Prep removed of 300 square metres of render in under five days, working around the high tides and some adverse weather, we saved our client thousands of dollars and over two weeks in a tight program and produced an ideal surface foe the new CP System and shotcrete to be applied.