Port Bonython Mooring Dolphins

Aqua Prep were engaged to carryout hydro demolition of two mooring dolphins at Port Bonython near Whyalla SA. The project which grew from a planned 68m3 to 99m3 required hydro demolition of the tops, sides. tapers and box beam on the underside. The majority of the works were undertaken via the Aqua Cutter and Aqua Spine with handguns used to tidy up around beams and fixtures.

Aqua Preps trailer mounted vacuum was used to remove the rubble from the deck requiring the product to be pulled 15m high through 40m of vacuum hose.